Biowatt-Biogas Project Briefs for Various Raw Materials
10,000-head Farm Biogas Project (2019)
Feedstocks:Cattle manure
 |
• Processing Capacity: Cattle manure 568 t/d
• Tank Volume: 4,000 m³ (effective) × 3 units
• Biogas Production: 14,423 m³/d; Average annual power generation 13,050 kWh/d
• Greenhouse Gas Emission Reduction: 58,000 tons of CO2 equivalent per year
|
 |
Modern Agricultural and Pastoral Circular Industrial Park (Manure Resource Utilization Project Part) EPC (2023)
Feedstocks:Cattle manure, spray water, electrical materials , milking parlor water, and other wastewater
 |
• Project Location: Dongying, Shandong
• Raw Materials: Cattle manure, spray water, electrical materials, milking parlor water, and other wastewater; 2,500 t/d during spraying season, 1,200 t/d during non-spraying season
• Biogas Production: 15,500 m³/d during spraying season, 23,100 m³/d during non-spraying season
• Bio-natural Gas Production: 3,000 m³/d
|
 |
552,000-head Swine Breeding Waste Resource Utilization Project (2020)
Feedstocks:Pig manure and breeding wastewater
 |
• Project Location: Chifeng, Inner Mongolia
• Raw Materials: Pig manure, daily processing of breeding wastewater 900 t/d
• Biogas Production: 8,000 m³/d
|
Multi-raw Material Mixed Waste Liquid Bio-natural Gas Preparation Industrialization Pilot Project (2016)
Feedstocks:Cassava residue, cassava stalks, and pig manure
 |
• Processing Capacity: Cassava residue 200 t/d, cassava stalks 50 t/d, pig manure 135 t/d
• Tank Volume: 5,000 m³ (effective) × 4 units
• Biogas Production: 40,000 m³/d, purified CNG 20,000 m³/d
|
Foods Songjiang Plant Waste Resource Utilization Project (2023)
Feedstocks:Sludge, potato peels, waste potatoes, and kitchen waste
 |
• Project Location: Songjiang District, Shanghai
• Processing Capacity: Sludge 8,500 t/year, potato peels 1,500 t/year, waste potatoes 6,005 t/year, kitchen waste 55 t/year
• Biogas Production: Average production of 4,000 m³/d from January to May; Average production of 8,000 m³/d from June to December
|
Bio-energy Reuse Project Phase II EPC - Low-concentration Anaerobic Digestion System Equipment Procurement (2021)
Feedstocks:Kitchen waste (Food waste)
 |
• Processing Capacity: 1,600 t/d kitchen waste
• Biogas Production: 146,880 m³/d
• Project Location: Laogang Ecological and Environmental Protection Base, Pudong New Area, Shanghai
• Tank Size: Φ23m × H23.5m (8 units), effective volume 9,200 m³
|
200 t/d Kitchen Waste Biogas Power Generation Project (2016)
Feedstocks:Kitchen waste (Food waste)
 |
• Tank Volume: 4,400 m³ (effective) × 2 units
• Biogas Production: 14,000 m³/d; Power generation: 28,000 kWh/d
|
"Adopt A Cow" Dairy Product Wastewater Treatment Project (2020)
Feedstocks:Milk processing wastewater
 |
• Processing Capacity: Milk processing wastewater 3,000 t/d
|
Wastewater Treatment Plant Renovation Project (2023)
Feedstocks:Brewing wastewater (Distillery wastewater)
 |
• Project Location: Zunyi City, Sichuan Province (Note: Zunyi is in Guizhou Province)
• Processing Capacity: 2,000 t/d brewing wastewater
• Discharge Condition: Effluent quality stably meets the Table 3 direct discharge standards of the "Discharge Standards for Water Pollutants from Fermented Alcohol and Baijiu Industry" (GB27631-2011)
|
Large-Scale Biogas Project (2019)
Feedstocks:Corn stover, cattle manure, and pig manure
 |
• Processing Capacity: Corn stover 30 t/d, cattle manure 400 t/d, pig manure 150 t/d
• Biogas Production: 20,000 m³/d
• Process: Wet desulfurization system 1,100 m³/h × 1
• H2S Concentration: 5,000 ppm, reduced to < 20 ppm after desulfurization
|
Livestock and Poultry Breeding Waste Comprehensive Utilization Pilot Project (2014)
Feedstocks:Chicken manure
 |
• Processing Capacity: Chicken manure 550 t/d
• Biogas Production: 20,000 m³/d
• Process: Wet desulfurization system 1,100 m³/h × 1
• Natural Gas: 20,000 m³/d
|
Livestock and Poultry Breeding Waste Comprehensive Utilization Pilot Project (Phase I 2008 / Phase II 2015)
Feedstocks:Chicken manure
 |
• Processing Capacity: Chicken manure 1,000 t/d (300 tons for Phase I, 700 tons for Phase II)
• Biogas Production: 100,000 m³/d
• Natural Gas: 42,000 m³/d
• Generator: 3 MW
|
 |
If you would like to learn more, please feel free to contact us.