Biogas and Resource Utilization : A Collection of Project Case Studies

Mar 18, 2026

Biowatt-Biogas Project Briefs for Various Raw Materials


 

 

10,000-head Farm Biogas Project (2019)

Feedstocks:Cattle manure

Three green anaerobic digestion tanks and a grey gas holder at Youran Dairy’s 10,000-head cattle farm biogas project.

• Processing Capacity: Cattle manure 568 t/d 

• Tank Volume: 4,000 m³ (effective) × 3 units 

• Biogas Production: 14,423 m³/d; Average annual power generation 13,050 kWh/d 

• Greenhouse Gas Emission Reduction: 58,000 tons of CO2 equivalent per year

Panoramic view of the biogas power generation facility showing green reactors and white gas purification equipment under a clear sky.

 

 

Modern Agricultural and Pastoral Circular Industrial Park (Manure Resource Utilization Project Part) EPC (2023)

 

Feedstocks:Cattle manure, spray water, electrical materials , milking parlor water, and other wastewater

Aerial view of the cattle manure resource utilization project in Dongying, featuring three white biogas digesters next to large livestock housing.

• Project Location: Dongying, Shandong 

• Raw Materials: Cattle manure, spray water, electrical materials, milking parlor water, and other wastewater; 2,500 t/d during spraying season, 1,200 t/d during non-spraying season 

• Biogas Production: 15,500 m³/d during spraying season, 23,100 m³/d during non-spraying season 

• Bio-natural Gas Production: 3,000 m³/d

Close-up of the bio-natural gas grid-connection facility with a red celebratory banner at the project site.

 

 

552,000-head Swine Breeding Waste Resource Utilization Project (2020)

Feedstocks:Pig manure and breeding wastewater

Wide shot of the swine waste-to-energy plant in Inner Mongolia, showing green anaerobic tanks and a white spherical gas storage tank

• Project Location: Chifeng, Inner Mongolia 

• Raw Materials: Pig manure, daily processing of breeding wastewater 900 t/d 

• Biogas Production: 8,000 m³/d

 

 

Multi-raw Material Mixed Waste Liquid Bio-natural Gas Preparation Industrialization Pilot Project (2016)

Feedstocks:Cassava residue, cassava stalks, and pig manure

Aerial shot of four large silver anaerobic digesters and a gas storage sphere for the cassava and pig manure biogas project in Guangxi.

• Processing Capacity: Cassava residue 200 t/d, cassava stalks 50 t/d, pig manure 135 t/d 

• Tank Volume: 5,000 m³ (effective) × 4 units 

• Biogas Production: 40,000 m³/d, purified CNG 20,000 m³/d

 

 

Foods Songjiang Plant Waste Resource Utilization Project (2023)

Feedstocks:Sludge, potato peels, waste potatoes, and kitchen waste

Industrial view of the waste-to-energy facility at PepsiCo Songjiang, showing metal tanks and piping for processing potato peels and sludge.

• Project Location: Songjiang District, Shanghai 

• Processing Capacity: Sludge 8,500 t/year, potato peels 1,500 t/year, waste potatoes 6,005 t/year, kitchen waste 55 t/year 

• Biogas Production: Average production of 4,000 m³/d from January to May; Average production of 8,000 m³/d from June to December

 

 

Bio-energy Reuse Project Phase II EPC - Low-concentration Anaerobic Digestion System Equipment Procurement (2021)

Feedstocks:Kitchen waste (Food waste)

Distant view of eight yellow anaerobic digestion tanks and four large white gas holders at the Laogang Ecological Base in Shanghai.

• Processing Capacity: 1,600 t/d kitchen waste 

• Biogas Production: 146,880 m³/d 

• Project Location: Laogang Ecological and Environmental Protection Base, Pudong New Area, Shanghai 

• Tank Size: Φ23m × H23.5m (8 units), effective volume 9,200 m³

 

 

200 t/d Kitchen Waste Biogas Power Generation Project (2016)

Feedstocks:Kitchen waste (Food waste)

Aerial view of the kitchen waste biogas plant in Xiaoshan, featuring two dark green digesters and a white gas storage tank in an urban industrial setting.

• Tank Volume: 4,400 m³ (effective) × 2 units 

• Biogas Production: 14,000 m³/d; Power generation: 28,000 kWh/d

 

 

"Adopt A Cow" Dairy Product Wastewater Treatment Project (2020)

Feedstocks:Milk processing wastewater

Construction and operation site of the milk processing wastewater treatment facility featuring four white circular tanks.

• Processing Capacity: Milk processing wastewater 3,000 t/d

 

 

Wastewater Treatment Plant Renovation Project (2023)

Feedstocks:Brewing wastewater (Distillery wastewater)

Bird's-eye view of the brewery wastewater treatment plant in Zunyi, showing mountainside pools and blue cylindrical treatment tanks.

• Project Location: Zunyi City, Sichuan Province (Note: Zunyi is in Guizhou Province) 

• Processing Capacity: 2,000 t/d brewing wastewater 

• Discharge Condition: Effluent quality stably meets the Table 3 direct discharge standards of the "Discharge Standards for Water Pollutants from Fermented Alcohol and Baijiu Industry" (GB27631-2011)

 

 

Large-Scale Biogas Project (2019)

Feedstocks:Corn stover, cattle manure, and pig manure

Exterior of the bio-natural gas project in Sheyang, showing green desulfurization towers and white purification units.

• Processing Capacity: Corn stover 30 t/d, cattle manure 400 t/d, pig manure 150 t/d 

• Biogas Production: 20,000 m³/d 

• Process: Wet desulfurization system 1,100 m³/h × 1 

• H2S Concentration: 5,000 ppm, reduced to < 20 ppm after desulfurization

 

 

Livestock and Poultry Breeding Waste Comprehensive Utilization Pilot Project (2014)

Feedstocks:Chicken manure

Sunset view of three green chicken manure biogas digesters and a white spherical gas holder on a grass field.

• Processing Capacity: Chicken manure 550 t/d 

• Biogas Production: 20,000 m³/d 

• Process: Wet desulfurization system 1,100 m³/h × 1 

• Natural Gas: 20,000 m³/d

 

 

Livestock and Poultry Breeding Waste Comprehensive Utilization Pilot Project (Phase I 2008 / Phase II 2015)

Feedstocks:Chicken manure

Reflection in the water of four large green anaerobic digesters at the Minhe chicken manure biogas power generation plant.

• Processing Capacity: Chicken manure 1,000 t/d (300 tons for Phase I, 700 tons for Phase II) 

• Biogas Production: 100,000 m³/d 

• Natural Gas: 42,000 m³/d 

• Generator: 3 MW

Dense rows of green fermentation tanks and multi-tower desulfurization systems at the Shandong Minhe project site.

 

 

If you would like to learn more, please feel free to contact us.